This means that it is easier to make a project than not to do it. But in fact, the project needs to be done. Now check it out.

3. Design

3.1. Design surveys, encumbrances

When constructing the facade, we increase the overall dimensions of the building. This value can be different, from 100 mm to 700 in my memory. In addition, often in the process of facade reconstruction, the owners decide to additionally arrange canopies over the entrances to the building or even porches – accordingly, this is an indent from the building up to 2 meters. Behind the facade, the blind area can also shift.

Therefore, at the design stage, it is necessary to check whether, after the reconstruction of the facade, the violation of the red lines, the boundaries of easements and the security zones of engineering networks will not occur – otherwise, you will have to dismantle everything that you mount in such areas.

3.2. Purpose, fire safety class of the building, height of the building

The parameters indicated in the title of the paragraph affect the requirements for the materials used, the arrangement of individual components of the facade structure, and further on the cost of work and materials. As a rule, most facing materials (granite, plaster, metal and composite panels) meet such requirements, but all kinds of PVC do not. The same with insulation, mineral wool – does not burn, polystyrene foam – is limited in use. In addition, heaters have restrictions on the height of the lined structures. In general, there are enough subtleties.

3.3. Inspection of the condition of walls and suspended structures

There is no point in explaining this. It is clear that all worn-out sections of the structures will need to be restored, which is not firmly fixed – it is necessary to remount. A project for such work is necessary by definition.

3.4. Fastener testing

During the examination of the walls, the type of facade anchors and insulation fasteners used is determined. It is not always possible to use conventional anchors, and chemical ones may be required. But the choice of fasteners is made not only by calculation methods, but is confirmed by acts of laboratory tests for pull-out directly at the object. Typically, pull-out tests cost about 5 – 10 thousand rubles. plus a round-trip if the facility is a long distance away, but manufacturers can do these tests at their own expense if you express interest in continuing to purchase and use the tested fasteners from them.

3.5. Thermal calculations and choice of insulation

This is generally a very important question, because. the cost of heaters ranges from 2000 to 9000 rubles / m3 , and possibly even higher. Expanded polystyrene heaters – provide better thermal insulation, but have limitations on use, because. are not non-combustible, unlike mineral wool . A combination of less dense (“cheap”) and denser (“expensive”) insulation materials is allowed to achieve optimal thermal insulation of the walls.

Often, customers have no idea about such subtleties and make a decision “by eye” and at a price – which is fundamentally wrong.

3.6. blind area

Depending on the chosen type of facade, its installation begins either directly from the blind area, or with an indent from it by 20 mm – if a ventilated gap is needed. Therefore, before performing facade work, it must already be completed.

But there is a certain problem with the blind area – this is the state of the soil and its seasonal swelling. The condition of the soil can spoil both a single flooding of the site, and a change in the state of groundwater, showers, etc. In this case, improper performance of work on the blind area may lead to its rise.





From practice, the lifting height can be both 50 and 100 mm. Accordingly, the pressure from the blind area passes to the facade elements, crushing them like an "accordion", shifting the facade subsystem along with the cladding. As a rule, a gap is made between the profiles for thermal expansion of the metal, but it is only about 10 mm. Considering everything, in the best case, only the facade of the first floor, or its lowest part, may suffer, in the worst case, the deformation of the facade will go higher.

Therefore, the development of a project and a survey of the state of the soil in terms of the blind area during the construction of the facade are mandatory.

3.7. seismicity

The choice of facade materials, fasteners, etc. the seismicity of the area in which the object is located. Therefore, in areas with high seismic hazard, the materials used must be certified for use in such conditions, and in the event of earthquakes, they must minimize the risk of injury during failure. This also makes adjustments to the final appearance of the facade, its technology and cost.

3.8. Gaps between metal elements of the facade

Often, customers want the joints between the individual panels of the facades not to be visible and ask to make the installation without gaps. Alas, due to the thermal expansion of metals, facing materials can become unusable, deformed. Even designers forget about it, but you must remember and demand compliance with these standards.

3.9. The layout project of the profile system, cladding and individual components of the facade

Only at this design stage it is possible to see the future appearance of the facade as close to reality as possible, to see the visualization, to understand the cost of work and the need for materials.

But, now we have to wait for the decision of the supervisory authorities … And only then either correct the project, or finally start the work in accordance with the current regulations.

5. Learn how to properly plan money for project management: principles of cash flow ( cash flow ) in practice

It often happens that with the growth of a company or the number of projects or contracts it is carrying out, difficulties arise with pla

The second moment, when there is more than one project and they are extended in time, it means that the receipt of funds (revenue) from them will also be extended in time, and at some point, expenses in one project have to be made at the expense of proceeds from another, to the detriment of of course the second. Well, if there are 5 or 10 projects … Plus, such moments as unforeseen circumstances that shift both the execution of work on the project and the receipt of revenue.

Therefore, it is extremely important to distribute the efforts (expenses) and income in such a way that the incoming funds are enough for everything and do not lead to insolvency in certain periods. Getting into such situations, enterprises are forced to look for opportunities to attract additional financial resources (loans), which increases costs even more, and besides, the very receipt of these funds is not always possible for various reasons. Therefore, cash flow pla

Let's see how to organize and simplify all this.

In fact, there is nothing more visual than a graph or a simple table. In our case, we need a schedule for the receipt and expenditure of funds. But in order to build it, you need to set up accounting for two things.